Date: 3 October 2026 Decided by: Owner, after a review of every card and document against the new direction
Release 1 was planned as a scripted app: hints as fixed archetype steps, a self-ticked structure checklist, and a fixed 2x / 5x ballpark rule. Reviewing the design showed three problems:
Judging any sound structure needs AI. Finishing the scripted version would mean building things to throw away, so Release 1 closed early and the AI work starts now.
A phone-first app where you answer a guesstimate in your own words and AI judges your structure against reviewed solution paths, so any sound approach earns credit. Questions, paths and ranges come from an agent pipeline that the owner approves, and the grader is tested before it is trusted. It shows the owner can take an AI product from discovery to a live, evaluated release with a human in the loop.
One week each.
| Release | Goal | Done when | Dates |
|---|---|---|---|
| R1 Discovery and foundations | Find out what the app needs and prove the basics work | Closed early. Delivered: archetype spike (#14), voice spike (#23), screen designs (#25), app shell (#26), answer editor spike (#37) | Closed 3 Oct 2026 |
| R2 AI grading | A live app where you answer in your own words and AI judges your structure | App live; 8 questions ready through the agent pipeline; grader catches at least 8 of 10 planted errors and grades the anchor examples at their intended level | 4 to 11 Oct 2026 |
| R3 Proof and help | Show the grading holds up, and help the user while answering | Repeatable grader test with logging; disagreement review on real attempts; AI hints with the guidance setting | 12 to 18 Oct 2026 |
| R4 Publish-ready | A finished piece recruiters can open and read | Public write-up of the build and evaluation; difficulty and skip; history | 19 to 25 Oct 2026 |
| Parked | Not committed | Progress by rubric dimension, notifications, mock interviewer, reference figures shown to the user, more questions, monthly figure check, text turned into rows, screen redesign | Reviewed 25 Oct 2026 |
About 40 hours of build. Agents work three streams in parallel, so the owner’s time is mostly review and testing: about 20 to 25 hours.
| Priority | Cards | Why |
|---|---|---|
| P0 | #48 Question file format, #51 Rubric with anchor examples, #47 Hosting and server spike | Everything else waits on these |
| P1 | #49 Agent pipeline, #27 Prepare 8 ready questions, #50 Band calculation, #52 AI grader, #38 Answer in my own words | The main build, in three streams: content (#49, #27), grader (#50, #52), app (#38) |
| P2 | #19 See how my structure was judged, #20 Check my number against the range, #53 Planted-errors check | The end of the chain; #53 is the done-when test |
If the week runs short, cut inside cards rather than dropping one: voice in #38 falls back to typed only, and #20 uses a simple fixed range instead of the calculated one.
Agreed details:
docs/reference/archetypes.md. No recalibration from attempts.| Card | Outcome |
|---|---|
| #9 Voice exchange (scripted) | Closed, merged into #38 |
| #15 Guided prompts by archetype | Closed, merged into #16 |
| #21 Reasoning feedback | Closed, merged into #19 |
| #38, #19, #20, #27 | Rewritten, Release 2 |
| #16, #17 | Rewritten or moved, Release 3 |
| #24, #7, #8 | Rewritten or moved, Release 4 |
| #22, #6, #10, #18 | Rewritten or moved, Parked |
New cards #47 to #59 cover the AI work.
docs/reference/archetypes.md (structure checklist plus 2x / 5x).docs/design/screens.md.docs/decisions/2026-09-27-release-1-moscow.md stays as the record of Release 1 planning.